What is relay coordination?

Relay coordination is the selection and verification of protection settings so the device closest to a fault operates appropriately while upstream devices provide backup protection.

What is a time-current characteristic (TCC) curve?

A TCC curve plots the operating time of a protective device against current. Engineers compare curves over the expected fault-current range to assess selectivity and backup operation.

What is the difference between IDMT and definite-time protection?

IDMT protection has a time that changes with the current-to-pickup multiple. A definite-time element operates after a configured delay when its pickup condition is satisfied. Their combined behavior depends on the selected protection scheme and the software model.

How does this website treat composite IDMT and definite-time elements?

Within the relay coordination study tool, the IDMT section applies below the definite-time pickup, and the definite-time section governs after that pickup. Verify this against the displayed composite TCC curve and chosen settings.

Why is transformer earthing important for earth-fault coordination?

Zero-sequence earth-fault current paths depend on transformer winding connections and neutral earthing. Upstream earth-fault element visibility cannot be assumed across a delta or an unearthed winding.

How is the coordination margin checked?

At a common study current, compare the operating time of the upstream backup device against the downstream primary device, using the modeled composite characteristics, fault-current transformations and required design margin.

Should motor starting be considered?

Yes. Starting current and starting duration may require a motor-start curve or other load constraints on the TCC plot so acceptable starting conditions do not cause unwanted relay operation.

Can study results be applied directly to a live plant?

No. Validate settings with approved single-line diagrams, short-circuit results, CT/VT ratios, relay manuals, site design philosophy, operating scenarios and the relevant IEC/IEEE guidance before implementation.